Difference between revisions of "Lube Machine At Bend Count"

From ATTWiki
Jump to: navigation, search
(Calculating the Value)
(Calculating the Value PER SHIFT)
Line 16: Line 16:
 
<ol>
 
<ol>
 
<li>Estimate the number of bends you may produce in a shift</li>
 
<li>Estimate the number of bends you may produce in a shift</li>
<li>Multiply the number of bends X 2</li>
+
<li>Multiply the number of bends X 2 to get BEND ARM MOVES per shift</li>
 
<li>Determine how many times you want to lube the machine during a shift.</li>
 
<li>Determine how many times you want to lube the machine during a shift.</li>
<li>Divide the ( Bends X 2 ) with the number of machine lubes you would like per shift</li>
+
<li>Divide the BEND ARM MOVES with the number of machine lubes you would like per shift</li>
 
</ol>
 
</ol>
  
 
<pre>
 
<pre>
 
2000 bends per shift
 
2000 bends per shift
2000 x 2 = 4000
+
2000 x 2 = 4000 Bend Arm Moves
Lube 3 times per shift, then...
+
If you want to lube 3 times per shift, then...
4000 / 3 (times) = 1333 bends (out and back)
+
4000 Bend arm moves / 3 times each shift = Lube every 1333 bends (out and back)
  
 
Lube Machine At Bend Count= 1333
 
Lube Machine At Bend Count= 1333

Revision as of 21:18, 28 January 2009

Cncbender logo.jpg


What is It?

This is a property in the CNCProcessor.cfg file. It is a bend count that instructs CNC Processor to enable the machine lube event when the bend count reaches a preset value.

Value

The value is set from 1 to any value greater than 1 like this:

Lube Machine At Bend Count= 4000

The value of 4000 in this example represents 4000 motions of the bend arm. Therefore, the machine would be lubed about every 2000 bends using the 4000 count.

Calculating the Value PER SHIFT

  1. Estimate the number of bends you may produce in a shift
  2. Multiply the number of bends X 2 to get BEND ARM MOVES per shift
  3. Determine how many times you want to lube the machine during a shift.
  4. Divide the BEND ARM MOVES with the number of machine lubes you would like per shift
2000 bends per shift
2000 x 2 = 4000 Bend Arm Moves
If you want to lube 3 times per shift, then...
4000 Bend arm moves / 3 times each shift = Lube every 1333 bends (out and back)

Lube Machine At Bend Count= 1333

Other Pages